alzamer escribió:BUENOS AIRES, Argentina--(BUSINESS WIRE)--
Central Puerto S.A. (“Central Puerto”) (CEPU), the largest private sector power generation company in Argentina, as measured by generated power, announced the approval of the Commercial Operation of a new cogeneration unit Luján de Cuyo with an installed capacity of up to 95.32 MW (net power output), starting on October 5, 2019 at 0:00 hs. (the “Commercial Approval”).
The cogeneration unit began its commercial operation 7 weeks earlier than the committed date, November 22, 2019.
Excelente noticia, la posteé el otro día... si dejaban pasar esas 7 semanas capaz se demoraba bastante la habilitación comercial. Deben ser otros 15-20 palos de EBITDA anuales.